Adding a second floor: what a real Needham permit tells you
By the H&N Custom Homes team ·

A second-floor addition usually means removing the roof, strengthening the structure, framing a new floor and roof, and reworking the first floor so the stair and ceilings work. The December 2020 permit for 62 Sachem Road in Needham, built by H & N, listed an estimated cost of $632,000.
Building up is the most satisfying kind of addition to watch. One week there is a roof, the next there is sky, then suddenly there are bedrooms. The neighbors notice. Their dog definitely notices.
What the Sachem Road permit actually says
Public permits are refreshingly blunt. The Needham permit for 62 Sachem Road, filed in December 2020 with H & N Custom Homes as owner of record, describes the job in one line: remove the roof, remove some first-floor walls to increase ceiling height, add a second floor and add a bay to the right side of the existing garage.
| Item | From the permit |
|---|---|
| Address | 62 Sachem Rd, Needham, MA |
| Date | December 10, 2020 |
| Scope | Remove roof; raise first-floor ceiling height; add second floor; add bay beside garage |
| Architect | Moran + Associates, Dedham |
| Engineer | Branagan Engineering |
| Estimated cost | $632,000 |
The main steps in a second-floor addition
- Design and engineering: an architect draws it and an engineer checks the structure can carry it
- Permits, filed with the drawings
- Weather planning, because a house with no roof is a house with opinions about rain
- Roof removal and structural reinforcement
- Framing the new floor, walls and roof, then closing it in quickly
- Mechanical, electrical and plumbing for the new floor
- Insulation, drywall, finishes and the new stair
The first floor gets better too
Notice the middle part of that permit line: removing first-floor walls to raise the ceiling height. A second-floor addition is a rare chance to fix the ground floor’s proportions while the structure is open. Put it in the plans from day one.
What drives the cost
Size, structure and finishes drive the number, and so does how much of the first floor changes. The only fair way to price one is from its drawings, which is why H & N quotes from plans and gives you that quote before work starts.